Michael Lyons
Engineering Design Process:
Step 1: Ask
The
problem presented in this situation was how to improve the design of the
Step 2: Imagine
The
design, materials, and the methodology used in this bridge too some time to develop.
At first we thought that we would use the same design as Tufts did which was a
roadway divided into several segments. Dwelling on the roadway we thought the
forces the hybrid steel/concrete bridge would be better mimicked the simplistic
design composed of two large segments. Basically we believed that the
multiplexed highway used in the Tufts design would be too unstable to perfectly
mimic the forces present in the actual
Furthermore,
we contemplated on how to construct the towers. The
Step 3: Plan
-See attached plan diagram
Materials:
- Aluminum 4 sheets 21 by 10 by .25
- Copper wire
- Plastic sheets
- 4 sheets 8 by .75 by 40
- 1 sheet 8 by .75 by 41.5
- 1 sheet 8 by .75 by 38.5
- Foam 4 sheets 21 by 10 by .5
- Eye Hooks 202 eyes hooks
- Instant cement Quart can
- Bonding agent One tube
Tool:
- Drill and bits
- Jigsaw
- Hammer
- Clamps
- Table Saw
- Wire cutters
- File
The bridge works because the opposite and opposing force balance out. This occurs because the roadway pulls down on the wires of the copper which then pull down on the towers. Since the towers are placed in the middle of the halves of the bridge then the force of gravity of one half pulling down on the copper wires will equal the other halfs pull. These forces are then balanced out in the tower because the equal forces pull in opposite directions. In the end the towers act as a ground for the entire bridge. Also the two halves of the bridge come together in a tongue and grove formation which allows the two sections of the bridge to connect and rest on each other so the entire structure does not tip over. We will test these forces by construction the bridge and allowing it to free stand for a week while changing the weight in the center of the bridge to accommodate different traffic situations.
Step 4: Create
We created a prototype of the bridge with the plans. The towers were going to be the most difficult piece of the bridge to design so they were cut out first from the aluminum sheets using the jigsaw. Once all four of the Aluminum pieces were cut out they were sanded and filed down to exact measurements. Then the foam pieces were cut to the same measurements as the aluminum sheets. Then two of the foam pieces were sandwiched in between the aluminum sheets. Then the bonding agent was applied and clamped together. After this we started work on the roadbed. We cut the plastic sheet to the exact specification of the drawn up blueprint and separated them into groups where the thirty-eight and a half inch and the forty-one and a half inch of the six sheets were sandwiched in between two of the forty inch plastic sheets. With these two groups representing each half of the bridge they were bonded together using instant cement and then clamped. Once everything had sufficiently dried holes were drilled in the appropriate locations for eye hooks. The eye hooks were then screwed into the drilled holes. Following the installation of the eye hooks the towers are then placed respectively into the center of a half of the roadway. Holding the tower and the roadway perpendicular to each other the copper wires were strung to support the bridge. Subsequently after the wires were strung the two halves of the bridge were connected and the bridge was completed.
The bridge was then tested by placing weights (5lb., 10 lb., 15 lb.) in the center of the roadway for a period of time. The longer the weights stayed on the bridge the more disfigured the bridges became. Basically what happened was that the weights in the center of the bridge created such an imbalance of force in the towers that the bonding agent broke. As a result the towers began to split apart and bend. Due to the results of this test we believe that what didnt work was the eye hooks in the tower and the copper wire. We also believe that using any type of metal wire or string would only cause more tension issues.
Step 5: Imagine
After much deliberation on the subject we decided that the copper wire could not carry the roadway because no matter how tight you made the wire it would never be at full extension. As a result the extra pull on one sides wire brought the roadway lower in elevation which created the extra pull to split the tower into several sections. We then decided to switch to using twine instead of copper wire so extra weight would not affect the tension because the twice length would already be at full extension. We also decided to drill hole all the way through the towers because then the weight distribution of the roadway would be evenly distributed throughout towers structure instead of focused a certain points.